Construction site update Hall 3 in Krieglach

Progress in the renovation of Hall 3

The DPB Rail Technical Service GmbH continues its growth path and expands the location in Krieglach with the extensive renovation of Hall 3.
Important steps have already been completed in recent weeks:

  • the facade of the hall was removed
  • all electrical installations were gutted
  • Preparations for the cleaning work of the hall supports
  • the pit foundations excavated
  • Work on the foundations for the future wheel lathe has started – these are to be completed by the end of February 2025

Further important construction phases are planned for the coming weeks (from week 7/2025):

  • the reinforcement of the working pit
  • track construction continues
  • Start of glass and roof work

With these measures, DPB Rail Technical Service GmbH is once again expanding its capacities in order to meet the increasing demands in the field of rail vehicle maintenance.

More to be announced…